In a briefing on Thursday, December 22, the Town notified residents that contractor A.F. Amorello & Sons has finished work for the season. Marathon Way will be used for material storage throughout the winter shutdown. Phase 3 of the project will begin after the Boston Marathon, which is scheduled for April 17.
- Phase 1 and 2 of the Main Street reconstruction have been completed. This work focused on the area from West Main to the Fire Station and the 135/85 intersection and included the full-depth excavation of these sections of Main Street and the installation of 2 of the 3 final paving courses.Â
- Winterization of the project is complete, including asphalt for driveways, sidewalks and wheelchair ramps. A base coat of asphalt has been placed for the shared-used path which will be plowed and used by all users during the winter. Â
- Traffic signals at the Wood Street and the 135/85 intersection have been completed. Â
- MassDOT will continue to coordinate with Eversource for utility work throughout the winter. In addition, MassDOT will continue to coordinate with subcontractors, including Premier Fence, who will be onsite in January to install the guard rail at CVS.Â